What are the key Community-led Development Programme dates in 2023 and 2024?

The key dates for the Community-led Development Programme in 2023 and 2024 are outlined in the table below:

 

Date 2023 Community-led Developmnent Programme deliverable
22 February 2023 Expression of Interest closes – Hāpai Hapori has received an Expression of Interest (EOI) from a community at this time so they can be considered in this programme cycle.  
29 March 2023  Close-off dates for Request for Partnership for the 2022/23 partnership round.
3 May 2023  Assessment of Request for Partnership completed.
8 June 2023  Crown Panel meeting.
22 June 2023  Communities notified and partnership discussions commenced.

 

 

Date 2024 Community-led Developmnent Programme deliverable
21 February 2024 Expression of Interest closes – Hāpai Hapori has received an Expression of Interest (EOI) from a community at this time so they can be considered in this programme cycle.  
27 March 2024  Close-off dates for Request for Partnership for the 2023/24 partnership round.
1 May 2024  Assessment of Request for Partnership completed.
6 June 2024  Crown Panel meeting.
26 June 2024  Communities notified and partnership discussions commenced.